Strata CTX100-S/CTX100 Installation

Installing the CTX100 Cabinet

2-Batteries/1-Cabinet

2-Batteries/2-Cabinets

Base Cabinet Power Supply

 

Black jumper wire

12 Volt

Base Cabinet Power Supply

+

Batteries

ABCS CN-BAT

80 AMP/

– Connnector

HR Each

 

 

ABTC-3M Cables (9 ft.)

 

10A Fuse

12Volt

Batteries

80AMP/ HR each

10A Fuse

+ ABCS CN-BAT

Connnector

Exp. Cabinet Power Supply

+ ABCS CN-BAT

Connnector

ABTC-3M Cables (9 ft.)

4-Batteries/1-Cabinet

12 Volt

Base Cabinet Power Supply

 

+

12 Volt

Batteries

Batteries

ABCS CN-BAT

80 AMP/

– Connnector

80 AMP/

HR Each

 

HR Each

 

 

All Jumper Wires

ABTC-3M Cables (9 ft.)

 

10A Fuse

 

must be 16 AWG Wire

 

 

 

4-Batteries/2-Cabinets

Base Cabinet

+

ABCS CN-BAT

– Connnector

Expansion Cabinet

+ ABCS CN-BAT

Connnector

5934

ABTC-3M Cables (9 ft.)

10A Fuse

Figure 3-9 Battery Wiring Diagram

4.Run the ABTC-3M battery cable from the batteries to the ABCS battery charger located in the CTX100 power supply. Dress the battery cable within the CTX100 cabinet(s) carefully (see Figures 3-10~3-13).

Important! The CTX100 must be connected to the live operating (hot) AC power source, and the power supply On/Off switch set to On prior to the final step of connecting the reserve power battery cable to the ABCS battery charger. If the batteries are connected after AC power is lost, reserve power will not function.

5.Connect the ABTC-3M battery cable two-prong female plug to the power supply “CN-BAT” receptacle on the ABCS charger.

6.To test reserve power operation, disconnect the system AC power plug from the source outlet while the power supply power On/Off switch in the On position. The AC and DC power lights should be Off. The system should continue to operate without interruption or dropped calls.

7.Plug the AC power cable back into the outlet; make sure the power supply switch is On.

3-12

Strata CTX I&M 06/04

Page 114
Image 114