Strata CTX Configuration

Primary/Reserve Power Cabinet Hardware

Cabinet AC Power Component Installation

After the cabinets have been floor mounted, the AC power components should be installed Tables 2-69and 2-70show the primary AC power components required for floor mounted systems.

Table 2-69 Floor Mount Cabinet Component Requirements for 120VAC Primary Power

Local

 

 

 

 

 

 

 

 

 

 

 

Electrical

1 Cabinet

2 Cabinets

 

3 Cabinets

 

4 Cabinets

 

5 Cabinets

 

6 Cabinets

7 Cabinets

Code

 

 

 

 

 

 

 

 

 

 

 

3 or more

 

 

1

-BCCB1201

1

– BCCB1201

1

– BCCB1201

1

– BCCB1201

 

cabinets

1 – BFIF

1 – BFIF

1

– RPSB2

2

– RPSB2

2

– RPSB2

N/A

require a

1

– BFIF

 

 

1

– BFIF

1

– BFIF

1

– BFIF

 

conduit box

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1. A BCCB120 conduit connection box must be installed and wired by a certified electrician per the local electrical code.

Table 2-70 Floor Mount Cabinet Component Requirements for 208VAC or 240VAC Primary Power

Local

1 Cabinet

 

2 Cabinets

 

 

3 Cabinets

 

4 Cabinets

 

5 Cabinets

 

6 Cabinets

 

7 Cabinets

Electrical

 

 

 

 

 

 

 

Code

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3 or more

 

1

– BCCB240

1

1

– BCCB2401

1

– BCCB2401

1

– BCCB2401

1

– BCCB2401

1

– BCCB2401

cabinets

1 – BACL240

 

1

– BPSB240

1

– BPSB240

2

– BPSB240

2

– BPSB240

3

– BPSB240

2

– BACL240

 

require a

1 – BFIF

 

3

– BACL240

4

– BACL240

5

– BACL240

6

– BACL240

7

– BACL240

1

– BFIF

 

conduit box

 

 

1

– BFIF

1

– BFIF

1

– BFIF

1

– BFIF

1

– BFIF

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1. A BCCB240 conduit connection box must be installed and wired by a certified electrician per the local electrical code.

Strata CTX Configuration

Strata CTX I&M 06/04

2-53

Page 99
Image 99
Toshiba CTX28 manual Cabinet AC Power Component Installation, Cabinet Cabinets, Local Cabinet