Connecting the Control Unit to the Network Interface

RJ21X Wiring Field Procedure

Follow this procedure to connect the RJ21X network interface to the control unit:

1 . Drill two diagonally opposite holes into the backboard for each piece of hardware. Keep a 1/16-inch (1.6 mm) space between each piece of hardware.

2 . Mount the wire troughs and the termination blocks.

There is a wire trough above and below each termination block.

3 . If necessary, repeat steps 1 and 2 for a second column.

4.Run the 25-pair amphenol cable on the RJ21X interface to the termination blocks.

If more length is needed, use an A25D male-connector, single-ended, 25-pair, non-plenum cable.

5.As needed, mount the D-rings to properly dress the wires.

6.Cut off the amphenol connector on the cross-connect field side and strip the wires for each of the 25 pairs.

7.Punch down the 25-pair wires to the termination block.

a.Route the wires through the fanning slots on the termination block.

b.Insert the conductors into the designated 110 connecting blocks already on the termination block.

c.Use the D-impact tool to seat the conductors (see Figure 4-4).

d.Remove any insulation fragments with a spudger.

8.Test the central office trunks for proper connection (see “Testing Trunks” later in this chapter).

Wiring 4-9

Page 186
Image 186
AT&T Release 2.0 manual RJ21X Wiring Field Procedure