Installing the Control Unit

Procedure

See the Control Unit Diagram on the back of System Form 1, System Planning, to determine the order of modules.

Once you have installed the power supply and the processor in the basic carrier, use the remaining slots for the modules as follows:

Basic carrier: slots 1 through 5

First expansion carrier: slots 6 through 11

Second expansion carrier: slots 12 through 17

Follow this procedure to install the modules, starting from Slot 1 (the first open slot next to the processor).

1.For each 400EM module trunk jack (numbered as ports 1 through 4 in Figure 2-16,check the System Planning Form 3d (Outside Trunks— Tie). If the E&M Signal column indicates 1C or 5 for a particular logical ID, set the DIP switches on the front of the 400EM module, as shown in Table 2-4and Figure 2-14.

NOTE:

The default E&M signal, 1S, does not require any adjustments in the DIP switches.

2.Remove the protective cover from each module’s gold-finger connector.

3.Lower the module onto the rod on the top of the carrier in the appropriate slot as shown in Figure 2-14.

4.Be sure that the connector on the module mates properly with the connector on the carrier.

2-56Installing the Modules

Page 95
Image 95
AT&T Release 2.0 manual Procedure