9 Example — Unspecified Connection from a PC Application
9.4.3Downloading the Project Engineering Configuration
Activity
1.
With “PLC " Download to Current Project " Selected Stations”, the project engineering data is loaded locally in the Station Manager on your PC.
Loading deletes the existing data on the relevant component and overwrites it with the new information.
Confirm with “Yes”.
The following message is displayed.
2.
Confirm with “OK” to complete the loading and to start the module.
124 | Commissioning PC Stations - Manual and Quick Start |
Release 5/2005 |