2 Getting Started “Configured Mode”
3.
4.
Steps in Project Engineering
Change to NCM PC Config / HW Config and enter the intended modules and applications (take them from the catalog).
(omitted if data entered by the PC Station Wizard)
The software applications that use communication services directly must also be specified in project engineering. One direct use is calling the
Optional:
If symbol tables were created for S7 stations in your project, you can make them accessible to the OPC server.
When you later import the XDB file or download the project engineering data to the PC station, these symbol tables are included.
Open the properties dialog of the OPC server to make your selection:
Commissioning PC Stations - Manual and Quick Start | 29 |
Release 5/2005 |