Model 9110T NOx Analyzer

Principles of Operation

Figure 13-7. Vacuum Manifold, Standard Configuration

Configurations will vary depending on the optional equipment that is installed. For example:

An 9110T with the optional internal span gas generator installed will add another FT8 connector and orifice assembly to the manifold where the FT28 fitting is shown in the above drawing.

An optional sample gas dryer will add a Tee-fitting so that two ¼” tubes can be connected to the same port.

13.2.1.2. Sample Gas Flow Valves and Routing

As discussed in Section 13.1, the measurement of NOx, NO and NO2 requires that the sample gas flow cycles through different routes that include and exclude various scrubbers and converters. There are several valves that perform this function:

The NO/NOX valve directs the sample gas either directly to the reaction cell or through the unit’s NO2 converter, alternating every ~8 sec.

The Auto Zero valve directs the sample gas stream to completely bypass the reaction cell for dark noise measurement once every minute, which is then subtracted as a measurement offset from the raw concentration signal.

Table 13-2: 9110T Valve Cycle Phases

 

NO/ NOX

Auto Zero

Time

 

 

Phase

Valve

Valve

Activity

Figure

Index

 

Status

Status

 

 

 

 

 

 

NO

Open to

Open to

0 - 2 s

Wait period (NO dwell time). Ensures reaction cell has

Figure

Auto Zero

been flushed of previous gas.

 

Measure

valve

reaction cell

 

 

13-3

2 - 4 s

Analyzer measures chemiluminescence in reaction cell.

 

 

 

 

 

 

 

 

 

 

Open to

 

4 – 6 s

Wait period (NOX dwell time). Ensures reaction cell has

 

NOX

Open to

been flushed of previous gas.

Figure

 

Measure

NO2

reaction cell

 

 

13-3

 

Analyzer measures NO + O3 chemiluminescence in

converter

6 – 8 s

 

 

 

 

 

 

 

reaction cell.

 

 

 

 

Cycle repeats every ~8 seconds

 

 

 

 

 

 

 