LaserSpeed 8000-3 Instruction Handbook
Appendix D: Supply Voltage Requirements
In order to deliver at least 20 volts to the
Quad Conductor Supply
If you are using four conductors (two supply, two return wires), the following table will help you determine your total voltage drop across the cable.
Wire Size | Wire Size | Voltage Drop per Foot | Voltage Drop per Meter |
(AWG) | (mm2) | (@2.0A) | (@2.0A) |
26 | 0.129 | 0.082 | 0.27 |
|
|
|
|
24 | 0.205 | 0.051 | 0.17 |
|
|
|
|
22 | 0.326 | 0.032 | 0.11 |
|
|
|
|
20 | 0.518 | 0.020 | 0.067 |
|
|
|
|
18 | 0.823 | 0.013 | 0.042 |
|
|
|
|
16 | 1.31 | 0.008 | 0.026 |
|
|
|
|
14 | 2.08 | 0.005 | 0.017 |
|
|
|
|
12 | 3.31 | 0.0032 | 0.010 |
|
|
|
|
Example: Your power supply is 200 feet (61 meters) away from the
Voltage Drop = #Feet * Voltage Drop/Foot = 200 * .020 = 4 volts
In order to deliver at least 20 volts to the
Note: All Beta LaserMike supplied cables have connections for quad conductor supply. In order to take advantage of all conductors, you need to be sure to supply power to both pins 24 and 25, and tie the two ground pins (12 and 13) together. The wires are not necessarily tied together inside the cable.
Part No. 93463 / Drawing No. | Page 203 of 221 | Revision A (Sep 2007) |