Overview and Roadmap
4.Connect battery leads.
5.Connect AC power or DC power.
6.Locate and connect Time Division Multiplexer (TDM) Bus.
7.Locate and connect
8.Install fibre optic cables between port networks (if the system has more than one cabinet stack).
9.Verify port cabinet address plugs.
10.Replace cabinet back panels.
11.Install ground plates.
12.Install cable clamps.
13.Install front plates (if needed for electromagnetic shielding and/or earthquake protection — see Appendix B, "Earthquake Protection Procedures").
14.Install cabinet clip (if you do not have earthquake protection or electromagnetic shielding).
Install Telecommunications Cabling
Complete this task by following the instructions provided in Chapter 5.
1.Install cross connect equipment.
2.Install cable slack manager.
3.Route cables from cabinet to
4.Connect control carrier outputs cable.
5.Label cables.
6.Install trunk cables among network interface, sneak fuse or circuit breaker panel, and switch cabinet.
7.Install coupled bonding conductor grounding.
Install Generic 3 Management Terminal (G3-MT)
Complete this task by following the instructions provided in Chapter 6.
1.Connect Management Terminal.
2.Set up Management Terminal.
3.Connect remote Management Terminal (if included).