Install and Connect the Cabinets | 4 |
|
This chapter describes how to install the Processor Port Network (PPN) and Expansion Port Network (EPN)
■Standard reliability
■High reliability
■Critical reliability
Refer to About This Book for a description of each configuration.
This chapter discusses
To install the cabinets, complete the following steps as detailed in this chapter:
1.Install earthquake floor mounting (if earthquake protection is required)
2.Position and stack cabinets
3.Connect grounds and Connect AC power or DC power
4.Connect Time Division Multiplexing (TDM) cables
5.Connect
6.Verify address plug settings
7.Install back plates
8.Install ground plates
9.Install front cabinet clips or ground plates
10.Connect
11.Install doors
Issue 1 September 1995