Plan and Prepare the Site

2

 

This chapter describes tasks required to plan, prepare, and provision the site depending upon which DEFINITY System Generic 3 was ordered. Perform the following:

Check the customer’s order.

Locate and lay out the equipment room.

Lay out and ensure appropriate power.

Lay out and ensure appropriate grounding.

Determine location of equipment closets.

Determine location of external trunk lines.

Create a provisioning plan.

Check the Customer’s Order

Determine what was ordered for the customer: DEFINITY System Generic 3, the number of cabinets, port networks, management terminals, adjuncts, consoles, telephones, modems, external trunks, etc.

NOTE:

One port network is equivalent to one single-carrier-cabinet stack. Throughout this document, “cabinet” sometimes refers to one single-carrier cabinet and sometimes refers to one stack of single-carrier cabinets, according to the context. An attempt has been made to use “single-carrier cabinet (SCC)” to mean exactly that and to use the more general term, “cabinet,” to mean a stack of one or more single-carrier cabinets or a port network. A “system” is one or more single carrier cabinet stacks.

Issue 1 September 1995 2-1

Page 27
Image 27
AT&T 555-230-894 manual Plan and Prepare the Site, Check the Customer’s Order