Locate and Lay Out the Equipment Room
4 | 8 |
1479
15
13
3
11 | 6 | 10 |
12 12
2
Figure Notes:
1.Printer (Optional)
2.Wall
3.Table
4.Trunk/Auxiliary Field. May be Located within
5.G3 Management Terminal
6.Processor Port Network (PPN) Cabinets
7.Cable Slack Manager
8.
9.Cable Slack Manager (Optional)
10.Expansion Port Network (EPN) Cabinets (optional). Space indicated by callouts 9 and 10 needed for each Expansion Port Network (EPN) in system.
11.22 Inches (55 cm)
12.27 Inches (68 cm)
13.32 Inches (81 cm)
14.40 Inches (101 cm)
Additional Notes:
AC receptacles must be separately current protected (fuse or circuit breaker) and not under the control of a wall switch. Receptacles must not be shared with other equipment and should be located away from the
System must be grounded by one of the approved methods. See Appendix A.
Earthquake protection and/or electromagnetic shielding may be required. See Appendix B.
Figure 2-1. Typical Floor Plan for G3i Single-Carrier Processor Port Network (PPN) with Expansion Port Network (EPN) Cabinets
Issue 1 September 1995