Locate and Lay Out the Equipment Room

4

8

1479

15

13

3

11

6

10

12 12

2

Figure Notes:

1.Printer (Optional)

2.Wall

3.Table

4.Trunk/Auxiliary Field. May be Located within Cross-Connect Field.

5.G3 Management Terminal (G3-MT)

6.Processor Port Network (PPN) Cabinets

7.Cable Slack Manager

8.Cross-Connect Field

9.Cable Slack Manager (Optional)

10.Expansion Port Network (EPN) Cabinets (optional). Space indicated by callouts 9 and 10 needed for each Expansion Port Network (EPN) in system.

11.22 Inches (55 cm)

12.27 Inches (68 cm)

13.32 Inches (81 cm)

14.40 Inches (101 cm)

Additional Notes:

AC receptacles must be separately current protected (fuse or circuit breaker) and not under the control of a wall switch. Receptacles must not be shared with other equipment and should be located away from the cross-connect field.

System must be grounded by one of the approved methods. See Appendix A.

Earthquake protection and/or electromagnetic shielding may be required. See Appendix B.

Figure 2-1. Typical Floor Plan for G3i Single-Carrier Processor Port Network (PPN) with Expansion Port Network (EPN) Cabinets