Test the System
Save Translations, if Required
If any administration changes have been made, save and make a back up copy of the translations. See Chapter 7, "Activate the System" for detailed instructions.
Re-install Front Doors
Put the doors back on the cabinets after all the system installation and test procedures are completed.
Next Steps
After the basic switch hardware is installed and tested, three more steps must be completed:
1.Install telephones and other equipment
These procedures are in Chapter 9, "Install and Wire Telephones and Other Equipment".
2.Administer features, telephones, and other equipment according to customer data found on the provisioning plan.
The data for system and telephone features can be administered using implementation procedures provided in the U.S. English book, DEFINITY Communications System Generic 3 Implementation,
3.Test telephones and other equipment.
These procedures are in Chapter 10, "Test Telephones and Other Equipment".
NOTE:
It may be more efficient to install each hardware component, administer it, and test it before going on to install another component. As an example, install the attendant console using the procedures in Chapter 9, "Install and Wire Telephones and Other Equipment", administer it using the procedures in the book listed above, and test it using the procedures in Chapter 8, "Test the System".