916 NTAK20Clock Controller daughterboard
An automatic switchover is initiated to the reference that recovers first. If the
secondary recovers first, then the clock controller tracks to the secondary;
however,it switches over to the primary when the primary recovers. If
the primary recovers first, the clock controller tracks to the primary and
continues to do so even if the secondary recovers.
If the command "track to secondary" is given, the clock controller tracks
to the secondary reference and continuously monitors the quality of
both primary and secondary references. If the secondar y goes out of
specification, the clock controller automatically tracks to primary provided
that is within specifications. On failure (both out of specification), the
clock controller enters the HOLDOVER mode and continuously monitors
both references. An automatic switchover is initiated to the reference that
recovers first. If the primary recovers first, the clock controller tracks to the
primary, butswitches over to the secondary when the secondary recovers.
If the secondary recovers first, the clock controller tracks to the secondary
and continues to do so even if the primary recovers.
Toprevent chatter due to repeated automatic switching between primary
and secondary reference sources, a time-out mechanism of at least 10
seconds is implemented.
If the command "track to primary" is given, the clock controller tracksto the
primary reference and continuously monitors the quality of both primary and
secondary references. If the primary goes out of specification, the clock
controller automatically tracks to secondary when the secondary is within
specifications. On failure (both out of specification), the clock controller
enters the HOLDOVER mode and continuously monitors both references.
An automatic switchover is initiated to the reference that recovers first. If the
secondary recovers first, then the clock controller tracks to the secondary,
then switches overto the pr imary when the primary recovers. If the primary
recovers first, the clock controller tracksto the primar y and continues to do
so even if the secondary recovers.
If the command "track to secondary" is given, the clock controller tracks
to the secondary reference and continuously monitors the quality of
both primary and secondary references. If the secondar y goes out of
specification, the clock controller automatically tracks to primary provided
that is within specifications. On failure (both out of specification), the
clock controller enters the HOLDOVER mode and continuously monitors
both references. An automatic switchover is initiated to the reference that
recovers first. If the primary recovers first, the clock controller tracks to the
primary, butswitches over to the secondary when the secondary recovers.
If the secondary recovers first, the clock controller tracks to the secondary
even if the primary recovers.
Nortel Communication Server 1000
Circuit Card Reference
NN43001-311 01.04 Standard
Release 5.0 23 May 2008
Copyright© 2003-2008, Nor tel Networks
.