EQQM104E EQQM115E
EQQM104E NO APPLICATIONS MET THE SELECTION CRITERIA
Explanation: No applications were found in the application description database, which met the selection criteria that
you specified.
System action: The system waits for you to respond.
User response: Change the selection criteria.
EQQM106E DEP OPTION MUST BE ONE OF
OCHCYES
,

ochpred

,

ochsucc

,

ochgrp

or
ochcno
Explanation: You have entered a value for the dependency resolution attribute that is not recognized by the MCP
dialog. You must change the value to one of the supported values defined by this message.
System action: The system waits for you to respond.
User response: Change the dependency resolution value.
EQQM107E BOTH DATE AND TIME MUST BE SPECIFIED FOR INPUT ARRIVAL
Explanation: Data entry error; see “Data Entry Errors” on page 2.
EQQM108E BOTH DATE AND TIME MUST BE SPECIFIED FOR DEADLINE
Explanation: Data entry error; see “Data Entry Errors” on page 2.
EQQM109E APPLICATION VALID-FROM IS LATER THAN PLAN END

MPLENDI

Explanation: The valid-from date and time of the occurrence you attempted to add to the current plan lie outside the
current plan end.
System action: The request is rejected. The system waits for you to respond.
User response: Change the valid-from date and time of the occurrence using the Application Description dialog.
EQQM110E OPERATIONS WITH DUPLICATE NUMBERS ARE SPECIFIED
Explanation: Data entry error; see “Data Entry Errors” on page 2.
EQQM112E THE OCCURRENCE CONTAINS UNCONNECTED OPERATIONS
Explanation: In the occurrence you are modifying, there is more than one network of dependencies. This is not
allowed.
System action: The modifications is rejected; the system waits for you to respond.
User response: Verify and correct the dependencies.
EQQM113E JOBNAME

MOJBN

MUST BE SAME IN JOB SETUP, PROCESS, AND PRINT
Explanation: The job name specified (

MOJBN

) for the job setup, process, and print operations must be the same.
System action: The system waits for you to respond.
User response: Verify and correct, for example, the dependencies or the job names.
EQQM115E A PROCESS OPERATION MUST PRECEDE A PRINT OPERATION
Explanation: A print operation must be preceded by a process operation.
System action: The system waits for you to respond.
User response: Verify and correct, for example, the print operation or the process operation.
Chapter 16. EQQMnnn Messages 177