EQQCL5YE EQQCL65E
|EQQCL5YE Not possible to define internal pred.
preopnum
to operation
opnum
|Explanation: OCL tried to define an internal predecessor to operation
opnum
, but a problem occurred.
|System action: OCL terminates.
|User response: Contact your IBM representative.
|EQQCL5ZE Not possible to remove the occurrence from the application group
|Explanation: OCL tried to remove an occurrence from the application group before deleting it from the current plan
|or from the long term plan. A problem occurred.
|System action: OCL terminates.
|User response: Contact your IBM representative.
|EQQCL60E Not possible to delete occurrence
appl
with IA
iadt
|Explanation: OCL tried to delete the occurrence
appl
, but a problem occurred.
|System action: OCL terminates.
|User response: Contact your IBM representative.
|EQQCL61E Not possible to delete operation
opnum
of occurrence
appl
|Explanation: OCL tried to delete operation
opnum
from the occurrence
appl
, but a problem occurred.
|System action: OCL terminates.
|User response: Contact your IBM representative.
|EQQCL62E Date must be supplied
|Explanation: A date must be supplied in the CHKDATE instruction.
|System action: OCL terminates.
|User response: Use the DATE1 or DATE2 keyword according with the format of the date, then resubmit the job.
|EQQCL63E Date not valid: date length cannot be > 10
|Explanation: An invalid date was specified in the CHKDATE instruction. Valid date formats are YYMMDD,
|YY/MM/DD, YYYYMMDD, YYYY/MM/DD, DDMMYY, DD/MM/YY, DDMMYYYY, and DD/MM/YYYY.
|System action: OCL terminates.
|User response: Correct the date, then resubmit the job.
|EQQCL64E Date not valid: date length cannot be < 6
|Explanation: An invalid date was specified in the CHKDATE instruction. Valid date formats are YYMMDD,
|YY/MM/DD, YYYYMMDD, YYYY/MM/DD, DDMMYY, DD/MM/YY, DDMMYYYY, and DD/MM/YYYY.
|System action: OCL terminates.
|User response: Correct the date, then resubmit the job.
|EQQCL65E Date not valid: format not recognized
|Explanation: An invalid date was specified in the CHKDATE instruction. Valid date formats are YYMMDD,
|YY/MM/DD, YYYYMMDD, YYYY/MM/DD, DDMMYY, DD/MM/YY, DDMMYYYY, and DD/MM/YYYY.
|System action: OCL terminates.
|User response: Correct the date, then resubmit the job.