EQQ2016E EQQ2018W
EQQ2016E OPERATION
OPERNR
IN APPLICATION
APPLID
IS TOO LARGE TO BE SAVED IN THE NEW
CURRENT PLAN DATA SET. THE FAILING OPERATION CONTAINS
PREDNR
DEPENDENCIES AND
SPECNR
SPECIAL RESOURCES
Explanation: The Daily Plan program was unable to create an operation record because it would be too large for the
output data set defined by the EQQNCPDS DD-statement.
System action: The Daily Plan program terminates processing.
User response: Reduce the number of dependencies or special resources for the failing application until all
operations in the application can be saved in the New Current Plan data set and resubmit the Daily Planning batch
job.
EQQ2017W AN OCCURRENCE WITH JOBNAME
JOBNAME
AND JOBNUMBER
JOBNUMB
FOR OPERATION
OPNUM
IS MISSING IN THE CURRENT PLAN RECORD TYPE 05 WITH INDEX NUMBER
OCCNUM
Explanation: The Daily Plan program was unable to find an index entry in the current plan record type 05 for the
occurrence with the specified operation.
System action: For occurrences that have been completed or deleted, Daily Planning takes the action defined by
the VALEACTION keyword of the BATCHOPT statement. In other cases Daily Planning is terminated with return code
08.
Problem determination: Refer to data in the diagnostic file, EQQDUMP, to determine the cause of the error.
User response: If no new plan is produced and the occurrence causing the problem is completed or deleted, rerun
Daily Planning with VALEACTION(W) specified in the BATCHOPT statement. In other cases save the EQQDUMP
output, create an APAR tape and contact your IBM representative.
EQQ2018W SPECIAL RESOURCE ERROR, REASON
RSN
Explanation: The Daily Plan program found an error when processing special resources.
System action: Daily Planning takes the action defined by the VALEACTION keyword of the BATCHOPT statement.
Problem determination: Refer to data in the diagnostic file, EQQDUMP, to determine the cause of the error.
User response: Contact your system programmer.
System programmer response: If no new plan is produced, resubmit the Daily Plan job with VALEACTION(W)
specified in the BATCHOPT statement. If a new plan has been created, use the OPC dialog to verify that the special
resource and operations using the special resource are correct. The dialog can be used to repair the inconsistency in
the current plan or current plan extension records. Take a copy of the EQQDUMP and if VALEACTION(A) was
specified save the dump and contact you IBM representative.
476 TME 10 OPC Messages and Codes