EQQ0601E EQQ0615W
EQQ0601E THE EXTENSION LENGTH SHOULD BE A NUMERIC VALUE FROM 0001 TO 1461
Explanation: The extension length must not be longer than 4 years, that is 1461 days.
System action: LTP batch processing ends.
User response: Update the extension length on the SYSIN statement and resubmit the job.
EQQ0602E AN EXTENSION LENGTH AND A START DATE CANNOT BE ENTERED TOGETHER
Explanation: You must specify either an extension length, or a start date and an end date.
System action: LTP batch processing ends.
User response: Update the SYSIN statement and resubmit the job.
EQQ0603E A START DATE REQUIRES AN END DATE TO BE SPECIFIED
Explanation: To simulate the LTP create function you must specify both a start date and an end date.
System action: LTP batch processing ends.
User response: Specify both a start date and an end date on the SYSIN statement and then resubmit the job.
EQQ0613I NO RESFILTER VALUES. REASON IS

noreason

Explanation: This message is issued by the DP batch programs to the EQQMLOG dataset when no filtering values
for resource reports can be found. The message variable contains the reason for this. The values below are
presented using the

noreason:

message variable.
NO RESFILTER DATASET NAME GIVEN
RESFILTER DATASET COULD NOT BE OPENED
DATASET DOES NOT CONTAIN ANY RESFILTER STATEMENTS.
System action: Daily Planning continues. There will be no reports of any kind produced for resources.
User response: This message does not necessarily represent an error. If resource reports are desired, correct - for
each reason above either:
The DP batch program SYSIN, if the RESFILTER dataset name was omitted.
The allocation of the dataset or PDS to be a FB 80 dataset. For this message reason, the dataset name given in
the DP batch SYSIN can be invalid or misspelled.
Verify that the name given in the DP SYSIN is correct. If it is, filter values must be given as RESFILTER
statements in this dataset.
EQQ0614W RESOURCE
RESNAME
IS EXCLUDED FROM PLANNING
Explanation: This message is issued by the DP batch programs to the Daily Planning report when a resource
definition was read in from the RD dataset, but did not pass the verification routines.
System action: Daily Planning continues. The resource will not be part of the planning process.
User response: Use the TME 10 OPC dialog to correct the specification of the resource.
EQQ0615W WORKSTATION

ENTNAME

IS EXCLUDED FROM RESOURCE
RESNAME
Explanation: This message is issued by the DP batch programs to the daily planning report, when a workstation
connect table entry does not represent a workstation in the current plan. The message variables are:

ENTNAME

The Work Station name
RESNAME
The name of the special resource.
System action: Daily planning continues.
User response: The message does not necessarily represent an error. Use the TME 10 OPC dialog to check the
workstation connect table to inspect (and possibly correct) the excluded entry.
Chapter 34. EQQnnnn Messages 467