EQQ0314E EQQ0318E
EQQ0314E WRONG OLD CURRENT PLAN SELECTED AS INPUT
Explanation: The old current plan dataset used as input when extending or replanning the current plan period is not
the correct dataset. The dataset may have been restored from a backup copy.
System action: The daily planning program is terminated.
User response: Ensure the daily planning batch JCL is referring to the same current plan and long-term plan
datasets as the controller subsystem. If you have restored the current plan incorrectly, set the CURRPLAN(NEW)
keyword in the JTOPTS statement and restart the TME 10 OPC controller to restore the current plan from the NCP
dataset.
Refer to

TME 10 OPC Customization and Tuning

for information about restoring TME 10 OPC datasets. Resubmit
the daily plan batch job when the error has been corrected.
EQQ0315E WORK STATION
WSN
DOES NOT EXIST
Explanation: The workstation
WSN
, which has work planned for it in the current plan, has been deleted from the
workstation description database.
System action: The daily planning program is terminated.
User response: Use the workstation description dialog to create the workstation description. And then use the Daily
Planning dialog to resubmit the job.
EQQ0316E WORK STATION
WSN
TYPE HAS BEEN CHANGED
Explanation: The workstation
WSN
type in the workstation description database has been changed for a workstation
that is part of the current plan.
System action: The daily planning program is terminated.
User response: Use the workstation description dialog to change the workstation type to its previous value. And
then use the Daily Planning dialog to resubmit the job.
EQQ0317W APPLICATION **************** ******** DOES NOT EXIST
Explanation: An application occurrence has been read in the long-term plan dataset, but there is no valid application
description
System action: The application is not included in the daily plan, and the application occurrence is marked deleted in
the long-term plan dataset. The daily planning program continues processing.
User response: Use the application description database to create the application description or change the
validation period. The application occurrence can be added to the current plan by using the Modify Current Plan
dialog.
EQQ0318E PERIOD START

SDATE

STIME
CANNOT BE CHANGED
Explanation: The period start date and time cannot be changed when extending the current plan period.
System action: The daily planning program is terminated.
User response: Use the Daily Planning dialog to get the correct start period value, and then resubmit the job.
Chapter 34. EQQnnnn Messages 443