EQQ0386I EQQ0389I
The dependency is selected according to the minimal impact criteria, that is, removal of this dependency causes
the least distortion to the present NET.
System action: No new current plan is created, TME 10 OPC continues normal processing. Reporting continues.
Problem determination: Information only. The Daily Plan program has terminated due to the loop condition.
User response: The operation identification given through these messages may be used to investigate and correct
the dependencies causing the loop. You may use the Application Description database dialog, or the Long Term Plan
dialog to correct the dependencies. If the loop is caused by an internal dependency, the most likely cause is the
Application Description, and should be corrected using that dialog. An external dependency may be corrected using
any of the above dialogs. When the error has been corrected resubmit the daily planning batch job.
EQQ0386I APPL **************** ******** **.** OP ******** WILL MISS DEADLINE
Explanation: The plan indicates that the operation specified in the message cannot meet its deadline. Possible
reasons for this could be: insufficient workstation resources, priority too low, and late predecessors.
System action: TME 10 OPC plans the operation so it is completed as close to the deadline as possible.
User response: If it is not acceptable that the operation be late, identify and modify the factor that is causing the
delay.
EQQ0387I APPL **************** ******** **.** WILL MISS APPL DEADLINE
Explanation: The plan indicates that the operation specified in the message cannot meet its deadline. Possible
reasons for this could be: insufficient workstation resources, priority too low, and late predecessors.
System action: TME 10 OPC plans the operation so it is completed as close to the deadline as possible.
User response: If it is not acceptable that the application be late, identify and modify the factor that is causing the
delay.
EQQ0388I APPL **************** ******** **.** OP ******** START > TAIL END
Explanation: The operation specified in this message cannot be planned to start until after the end of period.
Possible reasons for this could be: insufficient workstation resources or special resources, priority too low, and late
predecessors.
System action: The operation is planned to start at the end of period.
User response: Check the flagged operations and successors, and if unacceptable, extend the planning period or
alter the resource levels.
EQQ0389I APPL **************** ******** **.** OP ******** END > TAIL END
Explanation: The operation specified in this message cannot be planned to start until after the end of period.
Possible reasons for this could be: insufficient workstation resources, priority too low, and late predecessors.
System action: The operation is given an end time equal to the tail end time plus the operation duration. Potential
delays due to resource limitations are not considered.
User response: Check the flagged operations and successors, and if unacceptable, extend the planning period or
alter the resource levels.
Chapter 34. EQQnnnn Messages 453