Input Calibration

Step

Action

Screen

 

 

 

4Insert a screwdriver into the tab in the terminal board to be wired and pull. Slide the board half way out. There is a notch in the terminal board into which you can slide the retainer tabs and hold the boards in place while wiring.

5Label and remove the input wiring from the input terminals. Terminals 8 and 10.

(See Figure 7-6 Terminal Designations for ORP).

6Feeding the test wiring through the conduit hole in the case, connect a voltage supply to the 8 and 10 input terminals

To apply a signal in the range 0 to 1600 mV, connect the plus to

8 and the minus to 10.

To apply a signal in the range -1 to -1600 mV, connect the plus to 10 and the minus to 8.

Slide the Input board back and close the case and power up the unit. Do not apply power until the case is closed.

7

Calibrate

PV INPUT CAL

Press

 

 

In 1 pH/ORP Cal

 

 

 

In 2 Conduc Cal

 

 

 

 

 

 

 

 

 

 

 

 

Use

to select

 

 

Input 1 or 2 pH/ORP Cal

 

 

 

 

 

8

 

 

 

 

 

Enter

 

IN 1 pH/ORP Cal

 

Press

 

Sample Cal

0.000

 

 

 

 

ORP Offset

 

 

 

 

Reset ORP Offset

 

 

 

 

 

 

 

 

 

 

 

 

 

9

Put the unit in “Hold”

 

 

mode

 

 

 

 

10

Press Enter

The display will show the

 

Oxidation Reduction Potential in

 

 

Millivolts.

 

 

The value should match the

 

 

Input signal.

11Ignore the instructions to put the electrode in the reference solution. Instead, apply an appropriate millivolt signal (between –2000 and 2000 mV) to the input terminals.

To obtain a negative value, you must reverse the input to the unit as described in Step 5.

January 2009

UDA2182 Universal Dual Analyzer Product Manual

155

Page 167
Image 167
Honeywell UDA2182 manual Press