Honeywell UDA2182 manual Power Wiring Considerations, Installing Power Wiring

Models: UDA2182

1 258
Download 258 pages 46.92 Kb
Page 29
Image 29

Power Wiring

4.3 Power Wiring Considerations

Recommended wire size

Observe all applicable electrical codes when making power connections. Unless locally applicable codes dictate otherwise, use 14-gauge (2.081 mm2) wire for ac power, including protective earth.

Power supply voltage and frequency within specs

The power supply voltage and frequency must be within the limits stated in the specifications in Section 2.

4.4 Installing Power Wiring

Procedure

WARNING

Turn power off at mains before installing AC Power Wiring.

Do not remove boards with power ON.

WARNING

The ground terminal must be connected to a reliable earth ground for proper operation and to comply with OSHA and other safety codes. If metal conduit is used, connect a bonding wire between conduits. Do not rely upon the conductive coating of the instrument case to provide this connection. Failure to observe this precaution may result in serious personal injury.

CAUTION

To avoid damage to the case when connecting to a rigid metallic conduit system, the conduit hub must be connected to the conduit before the hub is connected to the enclosure

Table 4-1 Procedure for installing AC Power Wiring

Step

Action

 

 

1Check the tag on the outside of the case to be sure that the voltage rating of the unit matches the input voltage at your site.

ATTENTION

The Unit may be damaged if you apply power with the wrong voltage.

2With Power off, open the case:

Loosen the four captive screws on the front of the bezel.

Grasp the bezel on the right side. Lift the bezel gently and swing the bezel open to the left.

3Refer to Figure 7-1 for the location of the printed wiring board retainer. Loosen the two

January 2009

UDA2182 Universal Dual Analyzer Product Manual

17

Page 29
Image 29