Chapter4 Updating Device Firmware
Managing Firmware Jobs
4-14
User Guide for the CiscoWorks 1105 Wireless LAN Solution Engine
78-14947-01
Finishing the Job
To validate, save, and add the job to the list of scheduled jobs:
Procedure
Step 1 Click Finish in the left pane to complete job creation. The Finish dialog box
appears in the right pane. This dialog consists of an Email settings section, a
Remote server settings section, a Warnings section and a Validate and Save
section.
Step 2 Email settings section
If you want email notification of job completion, complete the Email settings
section:
Tip If email notification is not working, you may need to to set up the mail
route by specifying an SMTP server. See Specifying an SMTP Mail
Server, page 6-71.
Table4-5 Email Notification Settings for Firmware Jobs
Field Description
On completion, mail to Enter a comma-separated list of email addresses to
be notified when the job completes.
Email only if job fails Select this checkbox if you want recipients to be
notified only if the job fails.