1-12
Chapter 1 Using the Robot Safely
6 Trial Run
After making installations, adjustments, inspections, maintenance or repairs to
the robot, carry out trial run using the following procedures.
(1) If a safeguard enclosure has not yet been provided right after installa-
tion of the robot, rope off or chain off the movable range in place of
the safeguard enclosure, and observe the following points.
1. Use sturdy, stable posts that will not fall over easily.
2. The rope or chain should be easily visible by everyone around the robot.
3. Place a sign to keep the operator or other personnel from entering the
movable range.
(2) Check the following points before turning the controller ON.
1. Is the robot securely and correctly installed?
2. Are the electrical connections to the robot correct?
3. Are items such as air pressure correctly supplied?
4. Is the robot correctly connected to peripheral devices?
5. Have safety measures (safeguard enclosure, etc.) been taken?
6. Does the installation environment meet the specified standards?
(3) After the controller power is turned ON, check the following points
from outside the safeguard enclosure.
1. Does the robot start and stop as intended? Can the operation mode be
selected correctly?
2. Does each axis move as intended within the soft limits?
3. Does the end effector move as intended?
4. Are the signal transmissions to the end effector and peripheral devices
correct?
5. Does emergency stop work?
6. Are the teaching and playback functions normal?
7. Are the safeguard enclosure and interlock working as intended?
8. Does the robot move correctly during automatic operation?