Chapter 4 Periodic Inspections
3 Daily inspection
Check the following points before and after robot operation every day. Make adjustments and replacements as necessary.
Check point | Check items |
Safeguard enclosure | Check that the safeguard enclosure is securely |
| fixed at the designated position. |
Cables | Check for damages, dents and excessive bending. |
| Check for the adherence of chemicals. |
Motor, speed | Check for abnormal vibration or noise, and for |
reduction gear | abnormal temperature rise. |
Pneumatic devices | • Check that the air pressure is correct. |
| • Check that there are no air leaks. |
| • Check that the water has been drained. |
| • Check that the air filter is not contaminated. |
4 Three-month inspection
Check the following points every three months, and replenishing grease if re- quired. (To replace grease, see “7 Replenishing the grease”.)
Check point | Check items |
| • Clean off any dirt or contamination. Replenish |
| the grease after cleaning. |
Replenishment of | • Replenish grease if the items on the left are dry |
grease to X, Y and Z | or do not have enough grease. |
axis ball screw, linear |
|
guide and ball spline | Standard specifications: Alvania No. 2 (Showa Shell) |
| Daphne Eponex No. 2 (Idemitsu) |
| Clean room specifications: |
|
|
!CAUTION
Use of grease not recommended by YAMAHA may lead to a drop in the ball screw, linear guide, ball spline and linear bushing shaft life. When using the clean room specifications, the degree of cleanliness may drop.