GuestWorks and DEFINITY ECS Release 9
Technician Handbook for Hospitality Installations
555-231-743 Issue 1
November 2000
Translations and Testing
216Switch-to-PMS Link Translations
Testing the Switch-to-PMS Link
To test the switch-to-PMS link, have the hotel designate a room for testing. Testing
the switch-to-PMS link includes the following:
Link testing with the RS232 mini-tester (page 217)
Netcon and data module testing (page 219)
PMS testing and status (page 220)
Database swap testing (page 221)
Check-in and check-out testing (page 222)
Message waiting testing (both manual messages and voice messag es)
(page 223)
Controlled restrictions testing (page 226)
Housekeeping status testing (page 227).
During the switch-to-PMS testing, you will use the list pms-down command often
to view events that may indicate problems with the link. These events are found in
“Appendix C — List PMS Down Events” on page 245.