Performance Assurance Checks

Performance Assurance Checks

The following performance assurance checks are designed to be completed to verify proper operation when:

The monitor has been installed

An assembly has been repaired

To verify the operation any time the unit is suspect.

The performance assurance checks fall into two parts:

1.Verification of overall operation by completing the Performance Assurance Test

2.Verification of plug-in module operation by completing the Functional Test procedures.

You can perform any of the checks in any order you choose. They are broken up here for organizational sake.

Performanc To verify your monitor works properly, perform the following

e Assurance performance assurance test:

Test

1.Connect the power cord to the monitor and plug it in to an AC power source.

2.Turn the monitor on by pressing the ON/OFF button. (The monitor should complete the start-up after a few moments.)

3.Observe that there is a screen display and no error codes.

If any error codes are displayed, refer to the chapter “Troubleshooting Instruments” in the Service Guide.

If the screen comes up blank, check that the external power cable is plugged in. If the screen is still blank, contact your biomedical engineering department or the Philips representative.