Carrier PC211 specifications Lag Chiller Shutdown Requirements, WATER/BRINE Deadband

Models: PC211

1 392
Download 392 pages 38.23 Kb
Page 102
Image 102

6.The configured LAG START TIMER entry has elapsed. The LAG START TIMER shall be started when the lead chiller ramp loading is completed. The LAG START TIMER entry is accessed by selecting Lead/Lag from the Equipment Configuration table of the Service menu.

When all of the above requirements have been met, the lag chiller is forced to a START mode. The PIC control then monitors the lag chiller for a successful start. If the lag chiller fails to start, the standby chiller, if configured, is started.

Lag Chiller Shutdown Requirements

The following conditions must be met in order for the lag chiller to be stopped.

1.Lead chiller COMPRESSOR MOTOR LOAD value is less than the lead chiller percent capacity plus 15%.

Note: Lead chiller percent capacity = 100 – LAG PERCENT CAPACITY

The LAG PERCENT CAPACITY value is configured on the Lead/Lag Configuration screen.

2.The lead chiller chilled water temperature is less than the CONTROL POINT plus 1/2 of the

WATER/BRINE DEADBAND.

3.The configured LAG STOP TIMER entry has elapsed. The LAG STOP TIMER is started when the CHILLED WATER TEMPERATURE is less than the CHILLED WATER CONTROL POINT plus 1/2 of the WATER/BRINE DEADBAND and the lead chiller

Page 102
Image 102
Carrier PC211 specifications Lag Chiller Shutdown Requirements, WATER/BRINE Deadband