Initial Start-Up Chec klist for 19XL Hermetic Centrifugal Liquid Chil ler
(Print and use for job file)

Cutler-Hammer® Solid-State Starters

1. Check that all wiring connecti ons are properly terminated to t he starter.
2. Verify that the ground wi re to the starter is insta lle d properly and is of suffici ent size.
3. Verify that the motor is pr op erly grounded to the star te r.
4. Check that all of the rela ys are properly seated in t hei r sockets.
5. Verify that the proper ac inp ut voltage is brought int o the starter. Refer to the cer t ified
drawings.
The order in which the soli d-state control module adju stment potentiomet er s ar e s et is

Click here for Initial Start-Up Checklist for 19XL Hermetic Centrifugal Liquid Chiller

This equipment i s at li ne vo lt a ge wh en ac po we r i s c on ne cte d. Pressing the STOP
button does not remove voltage. Use caution when adjusting the potentiometers
on the equipment.
WARNING !WARNING