8. Close valves 1a, 1b, 3, and 5.
9. Open isolation valv es 12, 13, and 14 (if present).
10. Proceed to Terminate Pumpdown Lockout tes t t o tu rn off water pumps and ena ble the
machine compressor for start-up.
Valve 1a 1b 2 3 4 5 8 11 12 13 14
Condition CCCCCCC