c. Turn on pumpout condenser water.

d. Run the pumpout until the compressor reaches 18 in. Hg vac (40 kPa abs.). Monitor

 

pressure at the LID and refrigerant gages.

 

 

 

 

 

 

 

e.

Close valve 1b.

 

 

 

 

 

 

 

 

 

 

 

 

f.

Turn off pumpout compressor.

 

 

 

 

 

 

 

 

 

g. Close valves 1a, 2, and 5.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Valve

1a

1b

2

3

4

5

8

11

12

13

14

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Condition

C

C

C

C

C

C

C

C

C

C

C

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

h. Turn off pumpout condenser water.

 

 

 

 

 

 

 

 

i.

Proceed to Pumpdown test on the LID to turn off machine water pumps and lockout

 

machine compressor.

 

 

 

 

 

 

 

 

 

 

 