Omron CS1W-CLK21-V1, CVM1-CLK21 Replacing a Controller Link Unit with a Relay Terminal Block

Models: CS1W-RPT01 CJ1W-CLK21-V1 CVM1-CLK21 CQM1H-CLK21 CS1W-CLK21-V1 C200HW-CLK21

1 401
Download 401 pages 33.98 Kb
Page 389
Image 389

Using the Relay Terminal Block

Appendix C

Relay Terminal Block

Connect the Relay

Terminal Block.

 

ON

 

O

1

SW1

N

2

TER

ON

1 2

SW

BAUD RATE

4. Attach the terminal block cover to the communications terminal block on the Controller Link Unit.

Relay Terminal Block

 

ON

 

O

1

SW1

N

2

TER

ON

1 2

SW

BAUD RATE

Connect the Relay Terminal Block.

Replacing a Controller Link Unit with a Relay Terminal Block

Use the following procedure to replace a Controller Link Unit with a Relay Terminal Block. The communications cables are left connected to the Relay Terminal Block during the procedure, and only the Relay Terminal Block itself must be disconnected from the Controller Link Unit and then connected to the new Controller Link Unit.

The following procedure describes only steps required for the Relay Terminal Block. Refer to 9-6-1 Replacing the Unit for details on the replacement operation.

1.Turn OFF the power supply to the PLC with the Unit to be replaced.

2.Remove the communications terminal block cover from the Unit.

3.Loosen the three screws on the communications terminal block. (If adjacent Units are close enough to in- terfere with work, remove the three screws.)

4.Remove the Relay Terminal Block with the communications cables still attached to it.

!CautionDo not allow the metal portions of the Relay Terminal Block or the communications cable crimp ter- minals to come into contact with any conductive material.

5.Replace the Controller Link Unit. Set the node number, baud rate, operating level, and terminating resis- tance switches on the new Unit to the same settings as the previous Unit. With the C200HX/HG/HE or CQM1H PLC, turn ON the power to the PLC, download the data that was backed up from the previous Unit to EEPROM in the new Unit, and then turn OFF the power again.

6.Remove the communications terminal block cover from the new Unit.

7.Loosen the three screws on the communications terminal block on the new Unit. (If adjacent Units are close enough to interfere with work, remove the three screws.)

8.Attach the Relay Terminal Block to the new Unit with the communications cables still attached to it, making sure to align the signal lines and shield line with the markings on the Controller Link Unit.

9.Tighten the screws on the communications terminal block to secure the Relay Terminal Block. The tighten- ing torque for the three communications terminal block terminal screws is 0.5 N·m.

10.Attach the terminal block cover to the communications terminal block on the Controller Link Unit.

11.Turn ON the power supply to the new Unit. (The power supply to other nodes should still be ON.)

366

Page 389
Image 389
Omron CS1W-CLK21-V1, CVM1-CLK21, CS1W-RPT01, CJ1W-CLK21-V1 Replacing a Controller Link Unit with a Relay Terminal Block