Input Calibration
0 to 2 Volts, 0 to 5 Volts, or 1 to 5 Volt Inputs – Input 2
Refer to Figure
Table
Volts – Input 2
Step | Action |
|
|
1Connect the copper leads from the calibrator to the Input #2 terminals as shown in Figure
2Place voltage source at zero before switching on.
3Do not switch voltage source ON/OFF while connected to the instrument.
Voltage +
Source
_
25 (no connection)


26 +
27 -
Copper Leads
Equal Length
Figure 5-9 Wiring Connections for 0 to 2 Volts, 0 to 5 Volts or 1 to 5 Volts
Input – Input 2
5.7 Input 2 Calibration Procedure
Preliminary Steps
•Apply power and allow the controller to warm up for 30 minutes before you calibrate.
•Please read Subsection 5.6 – before beginning the procedure.
•Make sure you have LOCK set to NONE. See Subsection 3.4 - Tuning Set Up Group.
Continued next page