DEFINITY Enterprise Communications Server Release 8.2
Upgrades and Additions for R8r
555-233-115 Issue 1
April 2000
Upgrading R5si/R6si to R8r EPN and Adding Memory
3-49Release 5/6si to Release 8r
3
Reconnect Cables
1. Behind each EPN cabinet p ower supply, set the circuit b reaker to OFF.
NOTE:
Powering down an EPN cabinet without powering down the PPN will
set off alarms. However, these alarms should c lear after power is
restored to the EPN.
2. Replace all cables that were labeled and removed .
3. Install the top and bottom rear c overs. Be sure the correct rear covers are
installed on the new J58890N Expansion Control Cab inet. Do not use
these rear covers on the port ca binets.
NOTE:
The rear covers for Release 8r control carriers may ne ed 2 detents (1
for the TDM/LAN cable and another for the ICC c ables). If the
Release 5/6si was upgraded to a critical reliabi lity Release 8r and
the EPN was originally an R1V3, replace the lower rear cover of port
cabinet “B” with a new cover (846307817) so the ICC cab les and the
new ground plate c an be installed between cabinets “A” and “B.”
Power Up the EPN Cabinet
1. Behind each EPN cabinet p ower supply, set the circuit b reaker to ON.
After about 40 seconds, EPN power and PPN/EPN communications return.
2. After power returns to the EPN and all trouble is cle ared, verify the
EMERGENCY TRANSFER CONTROL switch is set to AUTO. This restores
the system to the normal mode.
Install Rear Ground Plates (Systems with
Earthquake Protection)
1. Loosen the 4 screws at the bottom of the top cabinet and at the top of the
cabinet underneath the to p cabinet. See Figure 3-17.
2. Align the mounting holes in the rear g round plate over the bottom screws
in the top cabinet. See Figure 3-17.
3. Align the mounting holes in the g round plate with the 4 holes at the top of
the cabinet below the top cabinet. Slide the mounting plate down to seat
on the screws.
4. Check all TDM bus cab les and the ICC to be sure they are not p inched by
the plates.
5. Repeat Steps 1-3 until the rear ground p lates are installed between all
stacked cabinets.
6. Do not tighten the screws yet.