DEFINITY Enterprise Communications Server Release 8.2
Upgrades and Additions for R8r
555-233-115 Issue 1
April 2000
Multicarrier G2 Universal Module to R8r EPN
5-45High Reliability
5
Required Tools
The following tools and items may be req uired during the up grade:
High-intensity flashlight or AC d rop light
3/8-inch flat-blade sc rewdriver with a 10-inch shank (minimum)
5/16-inch and 1/4-inch soc kets with a ratchet and 10-inch extension
Long-nose pliers to disc onnect ground strap s and straighten bac kplane
pins
Static-proof or original circ uit pack pac kaging for transporting circuit
packs
Labels for identifying the p ort circuit pac ks and cables attac hed to the
rear of cabinets
Twelve spare #12 and #10 self-tapping s crews
Four spare carrier ground strap s
Wrist ground strap
Repair kit for backplane pins (KS-22876 L2 or equivalent)
One copy of each of the foll owing manuals:
DEFINITY Enterprise Communications Server Release 8
Maintenance for R8r
DEFINITY Enterprise Communications Server Release 8
Administrator’s Guide
Follow Routine Preventive Maintenance
Follow routine preventive maintenance proc edures on the system to be
upgraded. For information ab out the procedures and necessary equipment, refer
to the “Preventive Maintenance” section in
DEFINITY E nterprise Communications
Server Release 8 Maintenance for R8r
.
Label Cables
To make reconnecting the cables simp ler and more reliable, label b oth ends of
the connector cab les associated with the carrier to b e removed.