DEFINITY Enterprise Communications Server Release 8.2
Upgrades and Additions for R8r
555-233-115 Issue 1
April 2000
G3vs with Intel 386 or Risc Processor to R8r
4-16Upgrade Completion
4
Upgrade Completion

Install Remaining Hardware and Admin ister the

System

1. If the present system was removed to make room for the Release 8r
cabinet, skip to Step 3.
2. If the Release 8r cabinet was installed whi le the present system is in
service, return to ‘‘Remove the Present System’’ on page 4-7. Return to
this section when finished.
3. Connect all new and reusable I/O c ables to the Release 8r cabinet.
Cross-connect at the MDF as required.
4. Remove all reusable circuit pac ks from the present system and install into
the Release 8r cabinet. Install any new circ uit packs into the Release 8r
cabinet.
5. Install fiber optic c ables and administ er the fiber links as needed. Refer to

DEFINITY Enterprise Communications Server Release 8 Installation and

Test for Multicarrier Cabinets

.
6. Administer any new translations, as required .
Enable TTI
1. Type change system-parameters features and press Enter.
2. On the second screen, set the Enabled? field to y to activate the TTI
feature.
Check Link Status
1. Type display communication-interface links and pr ess Enter. Compare it
with the earlier status.
2. Type status link
number
and press Ente r. Repeat this step for each lin k.
Enable Scheduled Maintenance
1. Type change system-parameters maintenance and press Enter . Use this
screen to enable sched uled daily maintenanc e.
Resolve Alarms
1. Examine the alarm log. Resolve any alarms using

DEFINITY Enterprise

Communications Server Release 8 Maintenance for R8r
.