DEFINITY Enterprise Communications Server Release 8.2
Upgrades and Additions for R8r
555-233-115 Issue 1
April 2000
Adding or Removing Cabinet Hardware
6-92Add a Control Carrier (Add Duplication)
6
Relocate Port Carrier B
Refer to Add a Switch Node Carrier (High or Critical Reliability) to relocate the
removed port carrier.
Connect Management Terminal or PC
1. Behind control carrier “ A,” disconnec t the management terminal or PC
cable from the “TERM” connector , and reconnect the c able to the “DOT”
(duplication op tion terminal) connector.
Reseat DEFINITY LAN Gateway System
1. Reseat the LAN Gateway assembly into its bac kplane connectors.
Reseat DEFINITY AUDIX System
1. If a DEFINITY A UDIX Sy stem r esid es in the PPN o r an EPN ( where PPN
port carrier “B” was relocated), reseat the AUDIX assembly to its
backplane c onnectors.
Power Up System
1. At an EPN (where PPN port carrier “B” was relocated), se t the main circuit
break er to ON.
2. At the PPN, set the main circuit breaker to ON.
3. The system performs a level 4 rebooting process, loading the system
program and def ault or current translations from the disk. Rebooting takes
5 to 11 minutes.
NOTE:
Ignore alarms for now.
4. Type the reset system 4 and press Enter to c opy the translations from
removable media to memory.
5. Clear any alarms.
6. Type save translation [both] and press Enter if translation chang es were
made in Step 8.
7. Type restore disk [both] full and press Enter to cop y the translations from
removable media to disk.
8. Verify that the EMERGE NCY TRANSFE R CONTROL switch is set to AUTO.
This restores the system to the normal operating mode .