Adding or Removing Cabinet Hardware
6-132Add MCC Port Carriers
6
Power Up MCC Port Network
1. At the MCC port network, set the main circ uit breaker to ON.
2. The system performs a level 4 rebooting process, loading the s ystem
program and de fault translations from the disk. Rebooting takes 5 to 11
minutes.
3. Refer to “Initialization and Recovery” and “LED Interpretation” cha pters in
DEFINITY Enterprise Communications Server Release 8 Maintenance for
R8r
, for circuit pac k LED indications and management ter minal displays
that occur during system reboot.
4. After the system reboot is finished and all trouble cleared, verify that the
EMERGENCY TRANSFER CONTROL switch is set to AUTO. This restores
the system to the normal operating mod e.
Restart DEFINITY LAN Gateway System
1. Log onto the DEFINITY LAN Gateway.
2. When the main menu appears, select
Maintenance
.
3. Select
Reset System
from the
Maintenance
menu.
4. Select
Restart System
from the
Reset System
menu.
Enter Added Translations
1. Enter added translation d ata as applicab le using
DEFINITY Ente rpris e
Communications Server Release 8 Administrator’s Guid e
.
Resolve Alarms and Enable Alarm Origination
1. Examine the alarm log. Resolve any alarms using
DEFINITY Enterprise
Communications Server Release 8 Maintenance for R8r
.
2. If the Alarm Origination Activated field administration is alread y
set to y, be sure to enable Alarm Origination . Otherwise you do not need to
enable Alarm Origination (p roceed to the next section).
3. Type change system-parameters maintenance and press Enter.
The Alarm Origination Activated field was c hanged to Alarm
Origination to OSS Numbers to support more than 1 OSS.