4. Behind control carrier A of EPN cabinet 3:
Install a lightwave transceiver on c able connector at slot 3A 02.
NOTE:
Attenuators may be required for single mode fiber using a
300A Lightwave Transceiver
Connect the other end of the fib er optic cable to the lightwave
transceiver, just installed, at slot 3A02. See Figure 5-8.
Carefully attach the fiber optic cable (with cab le ties) to the wall of
the cable tray at the built- in cable tie positions.
At the top of the cabinet, c oil up the surplus fibe r optic cable and
attach it to the wall of the cable t ray.
Figure 5-5. Standard Reliability Release 8 with Two or Three Port Networks
Figure Notes
1. Cabinet 1 Processor Port Network
2. Cabinet 2 Expansion Port Network 1
3. Cabinet 3 Expansion Port
Network 2