Adding or Removing Cabinet Hardware
6-102Add a Switch Node Carrier (Standard Reliabi lity)
6
9. If a switch node carrier was installed in the “D” p osition, verify that the
ZAHF4 TDM/LAN bus terminator is installed at slot 02 of the switc h node
carrier “D”. See Figure 6-36.
If a switch node carrier is b eing installed in the “ E” position, verify that the
ZAHF4 TDM/LAN bus terminator is installed at slot 21.
10. Install the front trim plates on the “D” carrier.
11. Install the new power units into the “D” carrier. Install a 649A on the left
and right sides of the c arrier.
12. Connect the power cord s to the power units. The power cord s are the
white cables equip ped with plug s that are run through the slots in the front