DEFINITY Enterprise Communications Server Release 8.2
Upgrades and Additions for R8r
555-233-115 Issue 1
April 2000
Multicarrier G2 Universal Module to R8r EPN
5-58High Reliability
5
For Two Collocated Expansion Port Networks
1. Behind control carrier A of PPN cabinet 1:
■Install a lightwave transceiver on the c able connector at slot 1A 02.
NOTE:
Attenuators may be required for single mode fiber using a
300A Lightwave Transceiver
■Connect a fiber optic cable to the transceiver jus t installed.
■Carefully attach the fiber optic cable (with cab le ties) to the wall of
the cable tray at the built- in cable tie positions.
2. Behind control carrier A of EPN cabinet 3:
■Install a lightwave transceiver on the c able connector at slot 3A 01.
NOTE:
Attenuators may be required for single mode fiber using a
300A Lightwave Transceiver
■Connect the other end of the fib er optic cable to the li ghtwave
transceiver just installed.
■Carefully attach the fiber optic cable (with cab le ties) to the wall of
the cable tray at the built- in cable tie positions.
■At the top of the cabinet, c oil up the surplus fiber optic cable and
attach it to the wall of the cable t ray.
3. Behind control carrier A of EPN cabinet 2:
■Install a lightwave transceiver on the c able connector at slot 2A 02.
■Connect a fiber optic cable to the transceiver jus t installed.
■Carefully attach the fiber optic cable (with cab le ties) to the wall of
the cable tray at the built- in cable tie positions.
4. Behind control carrier A of EPN cabinet 3:
■Install a lightwave transceiver on the c able connector at slot 3A 02.
NOTE:
Attenuators may be required for single mode fiber using a
300A Lightwave Transceiver
■Connect the other end of the fib er optic cable to the transceiver just
installed.
■Carefully attach the fiber optic cable (with cab le ties) to the wall of
the cable tray at the built- in cable tie positions.
■At the top of the cabinet, c oil up the surplus fiber optic cable and
attach it to the wall of the cable t ray.