Adding or Removing Cabinet Hardware
6-104Add a Switch Node Carrier (Standard Reliabi lity)
6
Install Circuit Packs
1. Install the new circuit pac ks into carrier ā€œD.ā€ Use the decal and the
upgrade c onfiguration document (p rovided with the equip ment) as a
guide.
2. Install circuit pac k blanks in slots not equip ped with circui t packs.
Interconnect Port Networks
1. Behind the cabinet containing the switch node carrier (See Figure 6-37):
a. Connect the metallic intrac arrier cable (H600-278) to slots 1D01
and 1D02.
2. Behind switch node c arrier D of PPN cabinet 1 (See Figure 6-37):
a. For each EPN, install 1 lightwave transceiver on a cab le connector
with the following order of slots: 1D20, 1D03, 1D19, 1D04, 1D18,
1D05, and so forth.
b. Connect 1 end of a fib er optic cab le to each lightwave transc eiver,
just installed.
c. Carefully attach the fiber op tic cables (with c able ties) to the wall of
the cable tray at the built- in cable-tie positions.
3. Behind processor c arrier A of each EPN cabinet:
a. Install a lightwave transceiver on c able connector a t slot 1A01.
b. Connect the other end of the fib er optic ca ble to the lightwave
transceiver, just installed, at slot A01 .
c. Carefully attach the fiber op tic cable (with c able ties) to the wall of
the cable tray at the built- in cable-tie positions.
d. Coil up the surplus leng th of fiber optic c able, and carefully atta ch
the coil to the wall of the cable tray.
Table 6-9. TDM/LAN Connections
ā€œJā€ Number Carrier Type LHS Slot RHS Slot
J58890BB L1 Port 21 02
J58890BB L2 Port 21 01
J58890BB L3 Port 21 01
J58890AP Control 21 02