Nortel Networks 1000M warranty Installing DC power Page 105

Models: 1000M

1 458
Download 458 pages 7.95 Kb
Page 105
Image 105

Installing DC power Page 105 of 456

Example configuration #2

A 300 A system:

initial power shelf equipped with a System Manager SP and five 1500 W rectifiers

supplementary power shelf equipped with six rectifiers

initial distribution and battery connection panel with 18 plug-in positions for load protection devices and eight positions for battery protection devices

Example configuration #3

A 300 A system (see Figure 36 on page 106):

initial power shelf equipped with a System Manager SP and five 1500 W rectifiers

supplementary power shelf equipped with six rectifiers

initial distribution and battery connection panel with 18 plug-in positions for load protection devices and eight positions for battery protection devices

supplementary distribution panel with 26 plug-in positions for load protection devices

Communication Server 1000M and Meridian 1 Large System Installation and Commissioning

Page 105
Image 105
Nortel Networks 1000M warranty Installing DC power Page 105