Page 334 of 456 Powering up the system and initial loading

STAT XSM Check the system monitors

****Exit program

6Clear the display and minor alarms on both Cores:

LD 135

Load program

CDSP

Clear displays on the cores

CMAJ

Clear major alarms

CMIN ALL

Clear minor alarms

7Test the clocks:

a.Verify that the clock controller is assigned to the active Core:

LD 60

Load program

SSCK x

Get status of the clock controllers (x is “0” or “1”

 

for Clock 0 or Clock 1)

SWCK

Switch the Clock (if necessary)

****Exit program

8Verify that the Clock Controllers are switching correctly:

SWCK

Switch Clock

 

(Wait 30 seconds)

SWCK

Switch Clock again

9Check applications (CallPilot, Symposium, Meridian Mail, and so on.).

10Check dial tone.

End of Procedure

NN43021-310 Standard 02.01 December 2007

Page 334
Image 334
Nortel Networks 1000M warranty Stat XSM Check the system monitors Exit program