Page 308 of 456 Powering up the system and initial loading
8Make sure the green lights in all the module power supplies are lit before proceeding to the next column. The red LED for each column remains lit until the system reloads.
Once the system is running, reattach all covers and panels to the modules and columns. Module covers must be kept on so the air from the pedestal fans will be directed up through all the modules and out the exhaust vents in the top cap. When the module covers are removed, the upper modules are not cooled properly because the air escapes from the open module door.
If the module covers are left off and the system overheats, circuit cards will malfunction and, in extreme cases, melt.
End of Procedure
Installing software
Before you begin
Dependency Lists (DepLists) are the Nortel recommended Product Enhancement Packages (PEP) for a software release. As common practice, ensure that you have the latest issue of the DepLists at the time of system installation. The issue and date of the DepLists is shown on the software
If the software
Refer to the Product Matrix Dependency List User Guide, available on the Enterprise Solution PEP Library, for more information about accessing and using DepLists.
Software installation
Follow Procedure 55 to install the software. First install the software on Core/ Net 1, and then repeat the process to install the software on Core/Net 0.