Installing earthquake bracing Page 351 of 456

Procedure 66

Installing Kit B

1Locate the two mounting plates for each column over the anchor holes. Insert the anchors into the holes and tap the anchors into place with a mallet.

2Level the plates with shims. Leave the stack of shims exposed until all leveling has been completed (this will allow the addition or removal of shims if necessary).

3If the installation must meet CALIFORNIA OSHPD, tension proof load testing is required on 50% of the anchor bolts. These anchors must be tested to 6230 N (1400 lb) tension and 122 J (90 ft-lb) torque. Any failure requires testing of all remaining anchors.

4Go to “Installing earthquake rods” on page 351.

End of Procedure

Installing earthquake rods

The following tools are required to install the rods:

7.5 mm (5/16 in.) socket wrench

12.7 mm (1/2 in.) open-end wrench for rods

14.3 mm (9/16 in.) open-end wrench for nuts

Note: The earthquake rods should be installed before you position the columns.

Communication Server 1000M and Meridian 1 Large System Installation and Commissioning

Page 351
Image 351
Nortel Networks 1000M warranty Installing earthquake rods, Procedure Installing Kit B