Powering up the system and initial loading Page 331 of 456
a.Perform a visual check of the LCDs.
b.Test LCDs:
LD 135 | Load program |
TEST LCDs | Test LCDs |
DSPL ALL |
|
3Test the System Utility cards and the cCNI cards:
LD 135 | Load program |
STAT SUTL | Get the status of the System Utility card |
TEST SUTL | Test the System Utility card |
STAT CNI c s | Get status of cCNI cards (core, slot) |
TEST CNI c s | Test cCNI (core, slot) |
4Test system redundancy:
LD 137 | Load program |
TEST RDUN | Test redundancy |
DATA RDUN | Test database integrity |
STAT FMD | Status of one or both Fixed Media Devices |
| (FMD) |
STAT RMD | Status of one or both Removable Media Devices |
| (RMD) |
5Install the two system monitors. Test that the system monitors are working:
LD 37 | Load program |
ENL TTY x Enable the XMS, where x= system XMS
STAT XSM Check the system monitors
****Exit program
6Clear the display and minor alarms on both Cores:
LD 135 | Load program |
CDSP | Clear displays on the cores |
CMAJ | Clear major alarms |
CMIN ALL | Clear minor alarms |
Communication Server 1000M and Meridian 1 Large System Installation and Commissioning