Powering up the system and initial loading Page 331 of 456

a.Perform a visual check of the LCDs.

b.Test LCDs:

LD 135

Load program

TEST LCDs

Test LCDs

DSPL ALL

 

3Test the System Utility cards and the cCNI cards:

LD 135

Load program

STAT SUTL

Get the status of the System Utility card

TEST SUTL

Test the System Utility card

STAT CNI c s

Get status of cCNI cards (core, slot)

TEST CNI c s

Test cCNI (core, slot)

4Test system redundancy:

LD 137

Load program

TEST RDUN

Test redundancy

DATA RDUN

Test database integrity

STAT FMD

Status of one or both Fixed Media Devices

 

(FMD)

STAT RMD

Status of one or both Removable Media Devices

 

(RMD)

5Install the two system monitors. Test that the system monitors are working:

LD 37

Load program

ENL TTY x Enable the XMS, where x= system XMS

STAT XSM Check the system monitors

****Exit program

6Clear the display and minor alarms on both Cores:

LD 135

Load program

CDSP

Clear displays on the cores

CMAJ

Clear major alarms

CMIN ALL

Clear minor alarms

Communication Server 1000M and Meridian 1 Large System Installation and Commissioning

Page 331
Image 331
Nortel Networks 1000M warranty Dspl ALL