Cabling Common Equipment in a Multi Group system Page 221 of 456

Figure 92 on page 222 displays the COM and LAN cable connections.

CAUTION

Damage to Equipment

Label all cables on both ends before installation. Labels help ensure that the cables are properly routed and connected. Cable labels also help installers to troubleshoot problems and replace equipment.

Procedure 32

Installing the CP PIV to I/O panel cables

1Connect COM1 on the CP PIV faceplate to J25 on the I/O panel with cable NT4N88AA.

2Connect COM2 on the CP PIV faceplate to J21 on the back of the I/O panel with cable NT4N88BA.

3Connect the Dual Ethernet Adapter (RJ-45) for I/O Panel (NTRE40AA) to J31. Secure the adapter to J31 with the two screws included in the shipment.

4Connect LAN 1 (Ethernet) on the CP PIV faceplate to J31 (top) of the I/O panel with cable NT4N90BA.

This connection can only be made after the Dual Ethernet Adapter is installed (see step 3 above).

Note: If a LAN switch is not used, connect LAN 1 in Core 0 to LAN 1 in Core 1.

5Connect a crossover Ethernet cable (NTRC17BA) from the LAN 2 port in Core 0 to the LAN 2 port Core 1. This connection is for Core redundancy.

Note: To ensure EMI shielding, route the cable along the front of the card cage and through the sides of the Core/Net modules.

6Repeat steps 1 through 4 in the second Core/Net module.