DEFINITY Enterprise Communications Server Release 6 | Issue 5 |
Installation and Test for | May 1998 |
|
|
1Install and Connect Cabinets
Install System Cabinets | Page |
Install System Cabinets
Check the location of the AC power receptacles in the equipment room. The receptacles must be on a separately fused circuit not controlled by a wall switch. They must be located within 10 feet (3 m) of the cabinet and outside the Main Distribution Frame (MDF) area.
Position the PPN Cabinet
1.If the system is supplied with cable ductwork, space the cabinets on 32 inch (81.3 cm) centers
2.If the system is supplied with cable slack managers, place the cabinets far enough from the connection field to lay down the 32 inch (81.3 cm) slack managers and to provide a little extra room for the cables to access the cable slack managers.
3.If earthquake protection is required, skip to ‘Earthquake‘ Protection Installation’’ on page
4.If earthquake protection is not required, level the cabinets and adjust and lock the cabinet stabilizing bolts to keep the cabinet from moving.
5.At the bottom of the cabinet, install hole plugs (provided with cabinet) in the holes previously occupied by the 4 carriage bolts.
Position the EPN Cabinets
Each EPN cabinet is normally positioned adjacent to the PPN cabinet but may be located remotely in a different room or a different building.
1.The procedure for installing an EPN cabinet is the same as for the PPN cabinet.
2.If earthquake protection is required, skip to ‘Earthquake‘ Protection Installation’’ on page
3.If earthquake protection is not required, level the cabinets and adjust and lock the cabinet stabilizing bolts to keep the cabinets from moving.
![]()
NOTE:
To install a new EPN cabinet to an existing system, refer to DEFINTY Enterprise Communications Server Release 6 Upgrades and Additions for R6r.