DEFINITY Enterprise Communications Server Release 6

Issue 5

Installation and Test for Multi-Carrier Cabinets 555-230-112

May 1998

 

 

2Install Telecommunications Cabling

Cable Installation

Page 2-19

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Figure Notes:

1.Main Distribution Frame

2.AC Power Cord (AC-Powered Cabinets Only)

3.Cable Slack Manager Number 1

4.Trunk/Auxiliary Field

5.Station Distribution Field

r758432b MMR 052996

6.Cable Slack Manager Number 2

7.Cable Slack Manager Number 3

8.System Cabinet(s)

9.Building Cables (Through Cable Trough)

10.10 AWG (#25) (6 mm2) Wire to Coupled Bonding Conductor

Figure 2-11. Cable Routing to Bottom Terminal Blocks

Route Cables to Main Distribution Frame

The following guidelines should be followed when routing cables from the cabinet to the MDF.

■Each port cable is connected at the cabinet and then routed along the front trough of the cable slack manager to the connecting/terminal block where the cable is to be terminated.

■Enough slack must be left at the cabinet end of the cable to allow for proper dressing of the cables.

Page 72
Image 72
Lucent Technologies Release 6 manual Route Cables to Main Distribution Frame, Cable Routing to Bottom Terminal Blocks