DEFINITY Enterprise Communications Server Release 6

Issue 5

Installation and Test for Multi-Carrier Cabinets 555-230-112

May 1998

 

 

2Install Telecommunications Cabling

Cable Installation

Page 2-19

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Figure Notes:

1.Main Distribution Frame

2.AC Power Cord (AC-Powered Cabinets Only)

3.Cable Slack Manager Number 1

4.Trunk/Auxiliary Field

5.Station Distribution Field

r758432b MMR 052996

6.Cable Slack Manager Number 2

7.Cable Slack Manager Number 3

8.System Cabinet(s)

9.Building Cables (Through Cable Trough)

10.10 AWG (#25) (6 mm2) Wire to Coupled Bonding Conductor

Figure 2-11. Cable Routing to Bottom Terminal Blocks

Route Cables to Main Distribution Frame

The following guidelines should be followed when routing cables from the cabinet to the MDF.

Each port cable is connected at the cabinet and then routed along the front trough of the cable slack manager to the connecting/terminal block where the cable is to be terminated.

Enough slack must be left at the cabinet end of the cable to allow for proper dressing of the cables.

Page 72
Image 72
Lucent Technologies Release 6 manual Route Cables to Main Distribution Frame, Cable Routing to Bottom Terminal Blocks