2Install Telecommunications Cabling
Cable Installation | Page | |||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Figure Notes:
1.Main Distribution Frame
2.AC Power Cord
3.Cable Slack Manager Number 1
4.Trunk/Auxiliary Field
5.Station Distribution Field
r758432b MMR 052996
6.Cable Slack Manager Number 2
7.Cable Slack Manager Number 3
8.System Cabinet(s)
9.Building Cables (Through Cable Trough)
10.10 AWG (#25) (6 mm2) Wire to Coupled Bonding Conductor
Figure 2-11. Cable Routing to Bottom Terminal Blocks
Route Cables to Main Distribution Frame
The following guidelines should be followed when routing cables from the cabinet to the MDF.
■Each port cable is connected at the cabinet and then routed along the front trough of the cable slack manager to the connecting/terminal block where the cable is to be terminated.